Short Introduction of key Personal:

Mr. Mohan Bikram Karki/Chairman
Mr. Karki is one of the most successful hydropower developers of Nepal. The fact that he has already constructed 5 projects is an impressive feat in itself and speaks well of his leadership and managerial skills. He is currently undertaking his sixth project which is Chepe Khola Hydropower Project. Prior to his arrival in hydropower sector he was actively involved in import business. He is originally from Sindhupalchowk and maintains a strong connection with his birthplace. He is actively involved in numerous social organizations and rarely misses out in his social responsibility. He is a well spoken person with a proactive attitude and that reflects in his projects which never misses on their completion deadlines.
His involvement and experience are:
S.N. |
Designation |
Company |
Project |
Capacity |
Condition |
Remarks |
1 |
Chairman |
Mai Khola Hydropower Pvt. Ltd. |
Super Mai Cascade Hydropower Project |
3 MW |
Operation |
|
2 |
Managing Director |
Sagarmatha Jalabidhyut Comapany Pvt. Ltd. |
Super Mai-A Hydropower Project |
9.6 MW |
Operation |
|
3 |
Director |
Samling Power Company Pvt. Ltd. |
Mai Beni Hydropower Project |
9.51 MW |
Under-Construction |
|
3 |
Chairman |
Super Mai Hydropower Ltd. |
Super Mai Hydropower Project |
7.8 MW |
Operation |
|
4 |
Managing Director |
Suspa Bukhari Small Hydropower Pvt. Ltd. |
Kutheli Bukhari Small Hydropower |
1 MW |
Operation |
|
5 |
Chairman |
Himtech Business Pvt. Ltd. |
– |
– |
Chairman |
|
6 |
Director |
Snow Rivers Pvt. Ltd. |
Super Kabeli Khola-A Hydropower Project |
13.5 MW |
PPA Signed |
|
7 |
Director |
Hilton Hydro Energy Pvt. Ltd. |
Super Kabeli Khola Hydropower Project |
12 MW |
PPA Signed |
|
8 |
Director |
River Side Hydro Energy Pvt. Ltd. |
Tamor Khola-5 Hydropower Project |
37.52 MW |
PPA Signed |

Mr. Madhav Prasad Mainali/Managing Director
Mr. Mainali is a well known figure in the hydropower sector of Nepal. He was born in Dolakha and is actively involved in projects in different parts of the country. He is involved in a number of hydropower projects of which four projects are already constructed. Currently, he is undertaking his fifth project which is the ....................... hydropower project. He is a technically sound and curious person with excellent negotiation skills. The hydropower projects he has been involved have hugely benefitted from his commendable evaluation skills. He also has a prior experience of businesses regarding import and retailing of construction items. Owing to his keen interest and experience he has gained ample knowledge and expertise on overall management of the project.
His involvement and experience are:
S.N. |
Designation |
Company |
Project |
Capacity |
Condition |
Remarks |
1 |
Director |
Mai Khola Hydropower Pvt. Ltd. |
Super Mai Cascade Hydropower Project |
3 MW |
Operation |
|
2 |
Director |
Sagarmatha Jalabidhyut Comapany Pvt. Ltd. |
Super Mai-A Hydropower Project |
9.6 MW |
Operation |
|
3 |
Managing Director |
Super Mai Hydropower Ltd. |
Super Mai Hydropower Project |
7.8 MW |
Operation |
|
4 |
Director |
Suspa Bukhari Small Hydropower Pvt. Ltd. |
Kutheli Bukhari Small Hydropower |
1 MW |
Operation |

Mr. Rajendra Kumar BC / Designer/Director
Mr. B.C. holds M.Sc. in Water resource engineering (with specialization in hydropower and hydrology) from Tribhuvan University, Nepal. Mr. B.C. has more than twelve years of working experience in hydropower Engineering (especially design and implementation of hydropower projects). He has good analytical and managerial skill in hydropower sector. He has extensive experiences in conducting design, planning, implementation, management, monitoring and evaluation of hydropower project.
His involvement and experience are:
S.N. | Designation | Company | Project | Capacity | Condition | Remarks |
1 | Chairman | Units Engineering Consultancy Pvt. Ltd. | ||||
2 | Director | Sagarmatha Jalabidhyut Comapany Pvt. Ltd. | Super Mai-A Hydropower Project | 9.6 MW | Operation | |
3 | Director | Super Mai Hydropower Ltd. | Super Mai Hydropower Project | 7.8 MW | Operation | |